South Berkeley VFD (Company 20)
Line Item Title Name Budget Approved July 1, 2006 - June 30, 2007 Proposed Budget July 1, 2007 - June 30, 2008 Budget Approved July 1, 2007 - June 30, 2008
03 $0.00
04 $0.00
05 $0.00
303 Ambulance Authority
304 Extrication
411A Telephone - Main $3,500.00 $4,000.00 $4,000.00
411B Telephone - Sub $600.00 $800.00 $800.00
413A Utilities - Main $10,750.00 $11,000.00 $11,000.00
413B Utilities - Sub $3,600.00 $5,000.00 $5,000.00
414 Travel $500.00 $300.00 $300.00
415A M & R Buildings & Grounds - Main $4,500.00 $4,500.00 $4,500.00
415B M & R Buildings & Grounds - Sub $1,750.00 $2,500.00 $2,500.00
416 Maintenance & Repairs Equipment $8,500.00 $9,000.00 $20,350.00
417 Maintenance & Repairs Autos $12,000.00 $16,000.00 $16,000.00
418 Postage
421 Training And Education $3,000.00 $3,000.00 $3,000.00
422 Dues & Subscriptions
423 Professional Services
424 Audit Costs $1,200.00 $1,200.00 $1,200.00
441 Supplies & Materials $2,000.00 $2,500.00 $2,500.00
443 Automobile Supplies $9,000.00 $11,000.00 $11,000.00
445 Uniforms
29
30  
32
35
446 Turn-out Gear
426A Insurance - Vehicle $14,756.00 $14,930.00 $14,930.00
426B Insurance - Property $7,051.00 $7,000.00 $7,000.00
426C Insurance - Accident & Sick $3,361.00 $3,361.00 $3,361.00
426D Workers Compensation $2,500.00 $2,500.00 $2,500.00
427A Loan Interest $11,707.00 $13,575.00 $13,575.00
427B Loan Principle $41,568.00 $41,568.00 $41,568.00
47 Purchase for Inventory
TOTALS $141,843.00   $153,734.00   $165,084.00  
56 TOTALS  
South Berkeley VFD  Capital Fund Budget
507 Capital Outlay Equipment
Test All Ground Ladders $1,200.00
6 New Tires for Squad 25 $3,500.00
Recalibrate Co Monitors $850.00
Flow Test Scott Air Packs $1,400.00
Pump Work for Engine 20 $4,500.00
6 Complete Sets of Turn-out Gear $10,000.00
508 Capital Outlay Improvements
510 Capital Outlay Building
A Asphalt Front Apron to Road $11,000.00
Grading and Gravel to Parking Lot $1,600.00
Replace 8 Upstair Windows $3,500.00
Plumbing Upgrades $1,500.00
B Asphalt Front Apron to Road $8,000.00
Repaint All Interior Walls $3,500.00
Plumbing Upgrades $1,200.00
Total